Upgrades to Main St Water Mains
Upgrades to the Water Main on Main Street Hyannis from the Town of Barnstable, D.P.W. – Water Supply Division
Hans Keijser, Supervisor
Cleaning & Lining of 12″ Water Main on Main Street, from School Street to Bay View Street
Dear Customer:
The Hyannis Water System is continuing its program of cleaning and lining of water
mains to improve water quality. It is important to you that we maintain the water
distribution infrastructure, some of which is over I 00 years old. This water main
cleaning and lining project will be conducted in addition to the routine maintenance and
repairs performed by our operations and maintenance contractor, Suez.
Description of Work:
This project will clean and line the 12″ cast iron pipe installed in 191 I, replace valves, fire
hydrants, and customer water services up to the property line, on Main Street from School Street
to Bay View Street.
A temporary water bypass system will be installed to maintain a continuous supply of water.
The major work is anticipated to be done this fall 2019 with final paving to be completed in the
spring of 2020.
There will be an opportunity for you to learn more about this project, ask questions, make
comments, and voice your concerns:
• Thursday, September 12, 2019 at 6 P.M.
• Saturday, September 14, 2019 at IO A.M.
Location: Parking Lot, 200 Main Street